Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide not only helps you get the Microsoft certification, but also enables you to better understand the Microsoft technology. Killtesthave the right solutions for you to pass your 74-343 Managing Projects with Microsoft Project 2013 with confidence. We have the most advanced Microsoft 74-343 study materials that will help you pass your Microsoft Project 74-343 Exam. Each 74-343 resource available from Killtest has been hand crafted by our team of practicing 74-343 IT Professionals. Killtest is certain that your Microsoft 74-343 study materials are the highest quality, and customized to make the Killtest learning experience the best choice you can make in preparing for your 74-343 Managing Projects with Microsoft Project 2013 Certification. Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide are backed with 100% money back guarantee if you fail to take the exams in the first attempt. Our highly certified professionals team develops Microsoft Project 74-343 exam according to the latest Microsoft 74-343 updates.

Microsoft Project 74-343 Practice Exam | Killtest Microsoft 74-343 Test Questions | 2017 New 74-343 Study Materials

You are a project manager who uses Project Professional 2013.You are planning an office move, which will occur over a weekend.You use Auto Scheduled tasks and create a weekend working calendar.You need to assign the weekend working calendar to the task.What should you do? 
A.Click on the Task tab and select the Change Working Time button.Assign the weekend working calendar to the task. 
B.Assign the task calendar to the task using the Task Information dialog box. 
C.Right-click on the weekend on the Gantt chart and select the weekend working calendar. 
D.Change the start date of the task to the Saturday, which will assign the weekend working calendar to the task. 
Answer: B

You are a program manager for a complex software development project.You use Project Professional 2013 to manage your project.Your resources work on many different projects across the program, and you need to resolve resource overallocations.Your project team uses a resource pool to manage resources.Resource1 has been assigned to assist on a project that is on the critical path.After assigning Resource2 to the task, you notice that Resource1 is overallocated during the month of November.Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to. 
Using resource leveling in Project Professional 2013, you need to resolve the overallocation for Resource1 for the month of November only. 
What should you do? 
A.Set the priority of Project A to 1000 and the priority of Project B to 500.Change the leveling order to Standard, and select Level All. 
B.Set the priority of Project A to 1000 and the priority of Project B to 500.Set the Leveling Range for November.Change the leveling order to Priority, Standard.Select Level Resource, and choose Resource1 and Level Now. 
C.Set the priority of Project A to 500 and the priority of Project B to 1000.Set the Leveling Range for November.Change the leveling order to Standard and select Level Resource.Then choose Resource1 and Level Now. 
D.Set the priority of Project A to 500 and the priority of Project B to 1000.Change the leveling order to Priority, Standard, and select Level All. 
Answer: B

Your company uses Project Professional 2013.You have several projects that are part of a program, but you do not use Project Server.You use a Resource Pool file to share resources across all projects. 
You are informed that one of the projects is cancelled before it starts.As a result, you need to delete the project. 
What happens in the resource pool after you delete the project? 
A.The resource pool will prompt that the project is deleted the next time it is opened, allowing you to remove the project. 
B.The resource pool will still reflect the resource needs of the deleted project.You need to refresh the resource pool to fix the issue. 
C.The resource pool will still reflect the resource needs of the deleted project.You need to manually break the link to the deleted project. 
D.The resource pool is automatically updated when you delete the project. 
Answer: C

You are a project manager who uses Project Professional 2013.You work on a software development project, and the Project Management Office (PMO) requires you to enter project costs associated with all work completed on your project.You receive invoices for $5,000 for software licenses and $150 for supplies.Software licensing costs are associated with Task A: Obtain Software License.Supply costs are associated with Task H: Project Management Administration.You need to enter the costs into your project schedule.Which two steps should you perform? (Each correct answer presents part of the solution.Choose two.) 
A.Create a material resource for Supplies and Software License. 
B.Assign the Supply cost resource to Task H, assign the Software License cost resource to Task A, and enter the actual costs using the Task Usage - Cost table for both Task H and A. 
C.Assign the Supply material resource to Task H, assign the Software License material resource to Task A, and enter the actual costs using the Task Usage - Cost table for both Task H and A. 
D.Create a cost resource for Supplies and Software License. 
Answer: DB

You are a project manager who uses Project Professional 2013.When viewing the critical path, you notice that there are some inconsistencies.To investigate the status of the critical path, you insert the Total Slack column into a task table.You discover that many of the tasks have negative Total Slack values. 
You need to resolve the negative Total Slack values.What should you do? 
A.Re-assign resources that have more availability at the time of the negative slack. 
B.Remove lag time from task relationships. 
C.Remove as many constraints as possible. 
D.Remove lead time from the task relationships. 
Answer: C

With Microsoft 74-343 from Killtest, you can pass the 74-343 Managing Projects with Microsoft Project 2013 easily, get the Microsoft Project Certification and go further on Microsoft career path. Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide prepare you for Microsoft certification final exam. It prepares you for the kind of questions that you could expect with your final try. The Killtest Microsoft 74-343 test frames the questions and sets the paper the way you can expect in the real Microsoft certification exam. Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide will adequately prepare you for the topic areas you will be tested on in your real 74-343 Managing Projects with Microsoft Project 2013. Killtest offer you a comprehensive certification test solution to help you become Microsoft certified professional. Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide come with 91 real exam questions and answers that give you the experience of actual Microsoft Certification 74-343 Managing Projects with Microsoft Project 2013. Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide are very relevant to cover all the topics of curriculum of Microsoft 74-343 with very actual answers of every question.

Microsoft certification exam is becoming increasingly important for those who want to engage in IT industry. Now, It is possible to easily pass Microsoft 74-343 Killtest in your first attempt. Killtest will help you prepare well for your coming Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide with confidence. If you are looking to pass 74-343 Managing Projects with Microsoft Project 2013 exam, then Killtest is for you. Microsoft 74-343 test is one of the premier exams in the examination and certification industry. Advancing IT Professionals supplement their know-how with excellent Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide from Killtest. Killtest Microsoft 74-343 test questions are made by highly certified IT professionals whose experience in the field has led them to provide us with latest Microsoft 74-343 exam, before they are commonly available in the market. After using Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide, you will enter the Examination Hall with confidence of attempting Killtest Exam in first attempt.

Related Items

Categories : Microsoft Tags : Microsoft Project 74-343 Exam  74-343 Managing Projects with Microsoft Project 2013  Messages on MS Project Exam 74-343  74-343 MCP Microsoft Project 2013 Exam  74-343 Practice Exam  74-343 practice test  74-343 study materials  74-343 Test Questions  74-343 Training Materials  
Comments
Leave a comment